Ocean Express has consulted with government agencies in order to obtain all necessary permits in a timely manner. A summary of key project milestones are as follows:

February 2002 FERC application submitted
MMS application submitted
October 2002 FERC amended application submitted
November 2002 MMS amended application submitted
November 2002 Public Scoping Meetings at several locations along the route (FERC-hosted meetings where landowners and other interested persons can comment directly to FERC staff)
Period After
Scoping Meetings

Initial period for written public comment to FERC
on FERC on environmental issues

April 2003 Achieved Preliminary Determination from FERC
June 2003 FERC issued a Draft Environmental Impact Statement (DEIS). A public meeting to receive comments on the DEIS was held in Hollywood, Florida on July 28, 2003.
November 2003 FERC prepared a Final Environmental Impact Statement (FEIS). FERC concludes that approval of the proposed AES Ocean Express project with the appropriate mitigating measures as recommended, would have limited environmental impact.
January 2004 Received FERC Certificate authorizing construction, operation and maintenance of pipeline.

February 2004

Received Broward County Department of Planning and Environment Protection (DPEP) Environmental Resource License.
May 2004 Received Florida Department of Environmental Protection (FDEP) Environmental Resource Permit.
September 2004 FERC Amendment 2 application submitted
November 2004 MMS Amendment 2 application submitted
2Q 2008 Start pipeline construction
2Q 2010
Start deliveries to consumers

 

 