Ocean Express has consulted with government agencies in
order to obtain all necessary permits in a timely manner. A summary of
key project milestones are as follows:
| February
2002 |
FERC application submitted
MMS application submitted |
| October 2002 |
FERC amended application submitted |
| November 2002 |
MMS amended application submitted |
| November
2002 |
Public Scoping Meetings at several
locations along the route (FERC-hosted meetings where landowners and
other interested persons can comment directly to FERC staff) |
Period After
Scoping Meetings |
Initial period for written public comment to FERC
on FERC on environmental issues |
| April 2003 |
Achieved Preliminary Determination from FERC |
| June
2003 |
FERC issued a Draft Environmental
Impact Statement (DEIS). A public meeting to receive comments on the
DEIS was held in Hollywood, Florida on July 28, 2003. |
| November 2003 |
FERC prepared a Final Environmental Impact Statement (FEIS). FERC
concludes that approval of the proposed AES Ocean Express project
with the appropriate mitigating measures as recommended, would have
limited environmental impact. |
| January 2004 |
Received FERC Certificate authorizing construction,
operation and maintenance of pipeline. |
| February 2004 |
Received Broward County Department of Planning and Environment Protection
(DPEP) Environmental Resource License. |
| May 2004 |
Received Florida Department of Environmental Protection (FDEP) Environmental
Resource Permit. |
| September 2004 |
FERC Amendment 2 application submitted |
| November 2004 |
MMS Amendment 2 application submitted |
| 2Q 2008 |
Start pipeline construction |
2Q 2010
|
Start deliveries to consumers |